EU restrictions on inverters could cut European solar deployment by up to 6%, says Wood Mackenzie
Wood Mackenzie expects EU restrictions on inverters from high-risk suppliers to reduce cumulative solar and energy storage installations across the European Union by 3% between 2027 and 2030. Utility-scale solar and energy storage projects receiving EU funding account for most of the affected capacity.
In April 2026, the European Commission introduced restrictions on the use of inverters from high-risk suppliers in solar and energy storage projects receiving EU funding. The measures were implemented through internal guidelines for European financial institutions in response to concerns over cybersecurity and the security of energy infrastructure.
Utility-scale solar and energy storage projects receiving EU funding account for most of the affected capacity. Around 14% of European solar projects and 10% of energy storage projects rely on EU-backed loans or funds.
Wood Mackenzie said exposure is particularly high in Central and Eastern Europe due to the region’s greater reliance on EU funding and the strong presence of Chinese manufacturers. All China-based inverter manufacturers are affected by the country’s designation as a high-risk jurisdiction. Chinese suppliers accounted for more than 80% of European inverter shipments in 2025, with higher market shares in price-sensitive markets that rely more heavily on EU funding.
The research firm assessed the impact of the restrictions through interviews and surveys involving more than 30 industry stakeholders, including manufacturers, suppliers, distributors, solar and storage developers, and national solar associations. The study examines product availability, price increases, and contract renegotiations resulting from supplier changes.
Under its base-case scenario, Wood Mackenzie expects PV installations in key Central and Eastern European markets between 2027 and 2030 to be 6% lower than previously forecast. Energy storage installations are expected to be 5% lower on average. Romania, the Czech Republic, and Bulgaria are expected to be the hardest-hit markets due to their high exposure to EU funding restrictions.
The impact is expected to be less pronounced across the European Union as a whole. Wood Mackenzie forecasts a 3% reduction in cumulative solar and storage installations between 2027 and 2030. Western European markets are better positioned to absorb cost increases and have more established commercial relationships with inverter manufacturers not classified as high-risk suppliers. The impact is expected to peak in 2027, when Western supply chains will still have limited capacity to respond to the restrictions.
Wood Mackenzie estimates that inverter manufacturing capacity from suppliers not classified as high risk and available to the European market will exceed 150 GW by the end of 2027. This would be sufficient to meet European demand for solar and storage inverters, although actual availability will depend on distribution networks, logistics, after-sales services, and manufacturers’ ability to fulfill orders in individual markets.
Local product availability is one of the main challenges in Central and Eastern Europe. Some industry stakeholders said Western manufacturers could need months or even years to establish adequate distribution and after-sales service networks. Lead times for large orders could also increase, potentially delaying utility-scale projects.
However, the European Solar Manufacturing Council (ESMC) recently identified 212 GW of nominal inverter manufacturing capacity among European and other manufacturers not associated with high-risk countries, compared with EU demand of around 59 GW in 2025. While manufacturing capacity appears sufficient to meet demand, challenges remain in terms of local availability and after-sales services.
Rising costs represent another risk. Some developers said equipment cost increases of 1% to 5% could jeopardize projects with tight margins. Although inverters account for a relatively small share of total project costs, Wood Mackenzie estimates that switching suppliers could increase total system costs for solar and storage projects by 2% to 10%.
The impact is particularly significant for energy storage. A substantial share of battery energy storage systems (BESS) sold in Europe are supplied as AC blocks integrating batteries and inverters from a single manufacturer. Replacing integrated solutions from Chinese suppliers with separate battery and inverter systems could increase costs and complicate installation, system integration, and warranty management. Engineering, procurement, and construction (EPC) contractors and installers surveyed also anticipate additional training costs associated with adopting new inverter models.
Wood Mackenzie also modeled a more severe scenario involving an EU-wide ban on inverters from high-risk suppliers. Under this scenario, cumulative solar and energy storage installations in Central and Eastern Europe between 2027 and 2030 would be more than 18% and 13% below previous forecasts, respectively. Across the European Union, solar installations would be 11% lower and energy storage installations 13% lower, with the largest reductions occurring in 2029 and 2030.
At the time of publication of Wood Mackenzie’s analysis, the European Commission had yet to publish a dedicated document detailing its April 2026 decision.