Researchers at the University of Exeter in the United Kingdom have investigated the technical and economic feasibility of a green hydrogen-powered rail system supplied by agrivoltaics, vehicle-integrated photovoltaics (VIPV), and track-integrated photovoltaics (TIPV) and have identified grid-connected agrivoltaics as the most economically viable configuration, achieving a levelized cost of hydrogen (LCOH) of GBP 7.99 ($10.47)/kg.
“Our study presents an integrated framework for decarbonising UK railway transport through green-hydrogen-powered trains supplied by solar energy. Using the London Paddington–Penzance corridor as a case study, it investigates the integration of agrivoltaics, train-rooftop photovoltaics and track-integrated photovoltaics to meet the hydrogen production requirements of railway operations,” corresponding author Aritra Ghosh told pv magazine.
The researchers selected the 482 km Penzance–London railway corridor as a case study because conventional electrification faces challenges related to coastal exposure, tunnels, and high infrastructure costs.
The proposed system combines agrivoltaic electricity generation, rail-integrated PV, and a green hydrogen production and refueling hub in Penzance. Using PVsyst, HOMER Pro, and DSSAT, the researchers evaluated solar electricity generation, hydrogen production, economic performance, and crop responses to shading. Their methodology also incorporated system sizing, geospatial analysis, agricultural modeling, and techno-economic optimization.
For the simulations, the scientists considered retrofitting Class 800 trains with proton exchange membrane fuel cells (PEMFCs) and 350-bar compressed hydrogen storage. They also modeled a 1 MW agrivoltaic system featuring bifacial solar modules installed at a 30-degree tilt and 2.5 meters above the ground.
The 1 MW baseline system was subsequently scaled up to 114.4 MW, corresponding to an estimated annual electricity generation of 151 GWh, sufficient to meet the railway’s calculated annual hydrogen production energy demand on an annual energy-balance basis. The researchers also varied the initial ground coverage ratio (GCR) of 30.3% to assess its effects on crop yields and land-use efficiency.
For VIPV, the researchers simulated a 28.56 kW rooftop solar installation on a nine-car Class 800 train, accounting for shading, thermal conditions, and soiling losses. They also modeled a 194 kW TIPV system along a 500-meter railway segment, considering track geometry, vegetation shading, restricted cooling, and contamination.
The simulated energy yields were extrapolated based on available farmland, the 482 km railway corridor, and the operational train fleet. Agricultural modeling incorporated site-specific soil characteristics, including drainage, fertility, slope, and soil composition. The researchers also developed a coupled thermal and vapor-pressure model to estimate microclimatic conditions beneath the solar panels, considering interactions between crops, soil, PV modules, and ambient air.
The results showed that operating the entire route on hydrogen would require approximately 2,574 metric tons of hydrogen and 148.67 GWh of electricity annually. The agrivoltaic system was estimated to generate 151 GWh per year, compared with 104.45 GWh for TIPV and 0.70 GWh for VIPV.
The economic analysis identified the grid-supplemented agrivoltaic configuration as the most cost-effective solution, with a net present cost of GBP 263.07 million and an LCOH of GBP 7.99/kg. By comparison, the LCOH reached GBP 27.83/kg for an off-grid configuration oversized to meet demand on the worst solar generation day and GBP 28.11/kg for a system relying on seasonal hydrogen storage.
Although the grid-connected system could export surplus electricity during summer, winter electricity imports resulted in an estimated annual net grid-trading deficit of GBP 3.23 million.
The researchers also found that adding TIPV or VIPV increased lifecycle costs and reduced financial returns, making both technologies economically unattractive under the modeled conditions. The grid-connected agrivoltaic-only configuration achieved an internal rate of return of 18.39% and an estimated payback period of 5.41 years under the study’s financial assumptions.
The scientists acknowledged that hydrogen production costs remain above projected competitiveness targets, highlighting the need for financial support, further infrastructure optimization, and additional uncertainty analysis.
“Removing grid supplementation increased LCOH from £7.99/kg to £28.11/kg, an escalation driven by the scale of panel overbuild and storage infrastructure required to bridge the UK’s winter generation shortfall,” the researchers explained. “This result, together with the marginal contribution of rail-integrated PV, indicates that a grid-tied, centralised agrivoltaic architecture is both the technically simplest and the most economically robust configuration for a route of this scale.”
“Near-term deployment of hydrogen rail in the UK is better suited to shorter, non-electrified segments than to end-to-end intercity routes, supported by grid-tied agrivoltaics and, in coastal locations, seawater desalination rather than reservoir abstraction,” they concluded.
Their findings are available in the study “From pasture to platform integrating agrivoltaics and green hydrogen for the Penzance–London railway corridor,” published in Solar Energy.
Solar PV is gaining traction in the railway sector, with recent projects exploring its integration into tracks, railway infrastructure, and agricultural land near rail corridors.
In Austria, a 6.6 MW agrivoltaic facility was inaugurated in July 2026 in Donnerskirchen, Burgenland. The installation uses single-axis trackers and feeds electricity directly into the country’s 16.7 Hz railway power grid. Austrian Federal Railways (ÖBB) uses the solar electricity for rail operations, while organic farming continues on the same land, demonstrating the potential to combine agricultural production with railway electrification.
In Switzerland, startup Sun-Ways commissioned an 18 kW removable PV system on an operational railway line in the canton of Neuchâtel in April 2025. The installation comprises 48 solar modules positioned between the rails and is expected to generate approximately 16 MWh annually. The company is testing the technology’s performance, soiling resistance, and compatibility with railway maintenance operations, with the aim of enabling wider deployment of track-integrated solar systems.
Meanwhile, researchers at Germany’s Fraunhofer Institute for Solar Energy Systems (Fraunhofer ISE) identified 37.6 GW of potential PV capacity on land within 2 km of railway substations. The researchers estimated that these installations could generate approximately 32.9 TWh of electricity annually, more than four times the German railway network’s electricity demand in 2023. They also highlighted the importance of suitable inverters and direct connections to railway electricity networks to overcome technical and regulatory barriers.