More than 4.1 GW of large-scale solar projects advance across Mexico since September

More than 4.1 GW of large-scale solar projects advance across Mexico since September

Mexico’s utility-scale solar project pipeline continues to expand, with developments advancing across 15 states since September 10, according to a review of projects reported by pv magazine México.

Developers have submitted new environmental impact assessments to Mexico’s Ministry of Environment and Natural Resources (Semarnat), while other projects have secured environmental approvals, generation permits, equipment supply agreements or long-term electricity supply contracts.

Among the largest developments are a 621.17 MW solar plant in Veracruz, a 400 MW project in Jalisco and a 269 MW solar-plus-storage facility backed by a corporate power purchase agreement (PPA) in Coahuila.

November developments

In Veracruz, Semarnat has granted conditional environmental authorization to the 621.17 MW Cerro Colorado Solar project, promoted by Desarrollos y Soluciones Energéticas Eirene in the municipalities of Sayula de Alemán and Texistepec. The facility will feature 941,166 solar modules rated at 660 W and 1,803 Huawei inverters. The project covers approximately 1,063 hectares and includes battery energy storage, although its capacity has not been disclosed. Construction is expected to take two years. pv magazine México

In San Luis Potosí, Transformaes Creación Sostenible has submitted the 190.94 MW Parque Solar Peñasco project for environmental assessment. The development will have a nominal capacity of 150 MW and a 60.19 MW/240.77 MWh battery energy storage system (BESS). It will incorporate 289,296 Longi bifacial modules, Nextracker single-axis trackers and Power Electronics inverters, alongside Fluence Smartstack battery containers. Construction is expected to take 18 months.

In Jalisco, Negocios Renovables Inteligentes has submitted plans for the 400 MW Teuchitlán Solar project in the municipality of Tala. The proposed facility will incorporate 559,440 modules rated at 715 W, a 30 MW/60 MWh lithium iron phosphate battery system and a 9.3 km transmission line connecting the plant to the La Vega substation. The developer estimates an investment of $150 million and a construction period of 24 months.

In Campeche, Global Solar América 3 has obtained conditional environmental approval for its Planta Fotovoltaica Campeche project. The facility will be developed in two phases, increasing its installed capacity from 130.026 MWp to 180.08 MWp. The development will include 253,634 bifacial modules, battery storage and a 26.92 km transmission line. The project was previously selected under the mixed-investment scheme organized by Mexico’s Federal Electricity Commission (CFE).

In Coahuila, Atlas Renewable Energy and Mexican mining group Industrias Peñoles have signed a 20-year PPA supporting the development of a 269 MW solar-plus-storage project. The facility is expected to supply 550 GWh of electricity annually, with deliveries scheduled to begin in the first half of 2029. The project’s official name and battery storage capacity have not been disclosed.

In Jalisco, Mexico’s National Energy Commission (CNE) has granted a generation permit to the 120.71 MWac FV Cuquío project, developed by Green Park Energy, part of Spanish energy group Cox. The facility will incorporate 31.09 MW/96.23 MWh of battery storage and is expected to generate approximately 298.7 GWh annually. Construction is scheduled to begin in June 2027, with commercial operation targeted for December 2028.

Green Park Energy has also secured generation permits for its 145.31 MWac FV Villa Juárez project in Aguascalientes, incorporating 118.94 MWh of battery storage, and its 156.78 MWac FV San Diego de la Unión development in Guanajuato, featuring 137.22 MWh of storage.

In Quintana Roo, Semarnat has granted conditional environmental authorization to the 132.57 MWp/110 MWac Los Girasoles solar project in José María Morelos. The development, promoted by Hocofaisán Maya, forms part of a mixed-investment agreement between Polaris Renewable Energy and CFE. It will incorporate a 33 MW/101.5 MWh battery system and is expected to generate approximately 249 GWh annually. Commercial operation is targeted for November 2028. pv magazine México

October developments

In Campeche, Semarnat has granted environmental authorization to the 269.7 MWdc/198 MWac Santa Lucía Solar project. The facility will incorporate 738,920 photovoltaic modules. The environmental assessment process began in October 2019, with the latest resolution modifying the plant’s technical configuration and the area allocated to its infrastructure.

In Baja California, Invenergy Solar Development México has submitted environmental documentation for the Bura Energy Center, a photovoltaic development with a grid injection capacity of 38 MW and 238 MWh of battery storage. The proposed configuration stands out for its relatively large storage capacity compared with its grid injection target.

In Sonora, CFE has reported construction progress exceeding 27% for the 300 MW third phase of its Puerto Peñasco photovoltaic complex. The latest phase will incorporate approximately 563,000 solar modules. Installation of supporting structures began in September 2026, with commercial operation scheduled for December 2027.

In Veracruz, Solarig México has obtained conditional environmental authorization for its 56.4 MW El Guayabo Solar project in the municipalities of Medellín de Bravo and Tlalixcoyan. The development incorporates battery storage and will connect to CFE’s El Guayabo substation through a 115 kV transmission line. The environmental resolution provides five years for site preparation and construction and 30 years for operation.

In Campeche, Solarig México has secured conditional environmental approval for its 104 MWdc/75 MWac PV Moquel Solar project in Champotón. The facility will incorporate 162,342 photovoltaic modules and a 15 MW battery system with ten hours of discharge capacity, equivalent to 150 MWh. The environmental assessment process began in June 2024.

In Zacatecas, Fresnillo Solar is advancing the environmental permitting process for its 120.846 MWdc/100 MWac Fresnillo – PV Atocha project. The development will feature 164,416 bifacial photovoltaic modules and a 30 MW/112.5 MWh battery system. The planned investment amounts to approximately $101.5 million.

September developments

In Tamaulipas, Greendat Capital has submitted the 126.889 MWdc/100.2 MWac El Indio Solar project for environmental assessment in Altamira. The facility will incorporate 173,820 solar modules rated at 730 W, single-axis trackers and a 30 MW/90.27 MWh battery system. The development will cover approximately 269 hectares and connect to existing CFE infrastructure through a 5 km, 115 kV transmission line. Construction and site preparation are expected to take 26 months.

In Campeche, Copenhagen Infrastructure Partners (CIP) has advanced its La Alegría Solar development through a battery supply agreement with Chinese manufacturer CATL. The agreement covers a 313 MW/1,639.45 MWh BESS using CATL’s TENER technology, representing one of the largest battery procurement commitments associated with a Mexican photovoltaic development.

In the State of Mexico, Lagartija Solar has submitted plans for the 95.688 MW Ajolo Solar photovoltaic development in Hueypoxtla. The project will incorporate 132,900 bifacial modules rated at 720 W and a battery system capable of providing three hours of discharge. The development represents an estimated investment of MXN 1.4 billion and will connect to CFE’s Apasco substation at 230 kV.

Also in the State of Mexico, Tepetate Solar has submitted environmental documentation for its 105.3 MW Tepetate Solar project. The facility will incorporate 146,190 Jinko Solar bifacial modules and battery storage, with the definitive storage capacity to be determined following the corresponding grid impact study. The development schedule anticipates three years for preparation and construction, followed by 30 years of operation.

In Tlaxcala, Turquesa Energía has secured conditional environmental authorization for its 177.3 MW Parque Solar Miguel development in Hueyotlipan. The facility is designed to deliver up to 160 MW at its grid interconnection point. The environmental resolution establishes a 14-month period for preparation and construction.

In Nuevo León, Greendat Capital has submitted plans for the 125.991 MWp San Joaquín Solar project in Galeana. The facility will incorporate 172,590 modules rated at 730 W, single-axis trackers and a 30 MW/90 MWh battery system. The development will have a net grid injection capacity of 100 MW. Site preparation and construction are expected to take 26 months.

In Puebla, Semarnat has granted conditional environmental authorization for the 150 MW Impala Solar project in Tepeyahualco. The development covers approximately 669 hectares. Its generation permit indicates December 30, 2026, as the planned commercial operation date, although the actual construction status remains unconfirmed.

In Oaxaca, Mexican environmental authorities have approved the 92.1 MW PV Loma Bonita Solar development, promoted by PV Loma Bonita Solar SG. The project incorporates 12 MW of battery storage, with its environmental authorization allowing five years for site preparation and construction.

Additional private-sector projects

In November, CNE announced the approval of six private-sector solar projects representing a combined net generation capacity of 649 MW, 751.08 MWac of declared photovoltaic capacity and 627.94 MWh of battery storage.

In addition to the three Green Park Energy developments, the approvals include two projects promoted by Ammper Generación (Invex) in Tlaxcala and Morelos, and a development promoted by Viva el Sol in Coahuila. Commissioning of the portfolio is expected in 2028 and 2029. pv magazine México

Jalisco’s energy authorities are also monitoring the 395 MW Mesa Redonda project in Lagos de Moreno, the 118 MW Acatlán Generación development in Acatlán de Juárez and the 100 MW La Barca project. Their latest permitting and construction milestones remain unconfirmed.

Battery storage consolidates its position in Mexico’s solar market

The developments reported since September 10 illustrate the increasingly prominent role of battery energy storage in Mexico’s utility-scale solar sector.

Three-hour storage configurations feature across several projects, while developments such as La Alegría Solar, PV Moquel Solar and Bura Energy Center point toward longer-duration storage solutions designed to extend electricity delivery beyond daylight hours.

The growing pipeline also reflects a combination of private-sector investment, CFE-led developments and mixed-investment projects, with many of the facilities expected to enter commercial operation between 2027 and 2029.

Pipeline expansion

Mexico’s utility-scale solar market has shown signs of renewed investment activity since the second half of 2025. In October, the government announced plans to deploy up to 9.5 GW of solar and wind capacity by 2030, while Spanish energy group Iberdrola unveiled two PV projects totaling 535 MW. In November, pv magazine reported a new wave of large-scale solar and storage developments entering environmental assessment. The following month, Mexico approved 15 solar projects totaling approximately 2.47 GW, with commissioning expected between 2027 and 2029.

The momentum accelerated in 2026. In June, Mexico allocated 6.71 GW of solar capacity under a renewables tender. In September, pv magazine identified more than 3 GW of large-scale solar projects advancing across 10 Mexican states. In October, Mexico’s Ministry of Energy reported a development pipeline comprising 42 PV projects totaling 6.86 GW. More recently, research firm GlobalData raised its forecast for Mexico’s cumulative installed solar capacity to 43.8 GW by 2035, citing the country’s expanding project pipeline.