Golden State goes all in on VPPs
California built one of the biggest battery-based VPPs in the world with the Demand Side Grid Support (DSGS) program that began in 2023. More than 600 MW of battery capacity was enrolled in the program in 2026, most of which is aggregated from residential customers who each received an annual check for a couple of hundred dollars.
The downside of the program was that it relied on appropriations from the state budget and the legislature never gave it long-term funding. Project developers couldn’t present the value to customers when selling a system because they had no certainty the program would be there for more than a year. It was good value for the state – every dollar put in from the state budget resulted in $1.20 to $2 in rate reduction – but budget times are tight and funding anything is a struggle. The program is not funded for next year, though a narrower emergency response program will continue.
Another shortcoming of the DSGS was that it didn’t incorporate the value of avoiding utility spending on transmission and distribution. As we electrify everything, if we rely solely on the traditional approach of building bigger substations and more wires to faraway power sources, California’s already high rates will soar even higher.
Battery aggregators are capable of operating fleets differently behind each substation depending on the timing of local peak demand. Compensating us to do that can be cheaper than substation upgrades and line reconductoring.
In 2025, Governor Gavin Newsom vetoed all three of the bills the legislature passed on VPPs. Coming into the 2026 legislative session, there were some in the clean energy community that wanted to wait out Newsom’s final year in office and not put forward another VPP bill until 2027.
CALSSA and other coalition partners were committed to keeping the conversation going in the state legislature. We introduced multiple bills, and the message ended up resonating so well that two bills passed and were signed.
Policy progress
There is still a long road ahead. SB 913 directs the CPUC to include exports from behind-the-meter batteries in rating the effective capacity of customer systems. Currently, fleets of customer devices only qualify for utility capacity contracts to the extent each device reduces the consumption of the host customer. If any customer in a fleet allows energy to export to the grid, that energy is given zero value.
That’s a problem for customer batteries, because aggregators can’t commit more than a conservative estimate of how much energy each customer will be using at any time. If you make a large commitment of expected load reduction and customers don’t have high consumption during program events, energy spills on the grid and the value is negated. This results in penalties for non-performance even though the batteries did what they were supposed to do and the grid got the flexibility it needed.
When fleet operators can offer all the stored energy they know they can make available from their battery fleet, the capacity market will have more supply, which will bring down costs. For this to work, though, the CPUC must do more to recognize the reliability that customer batteries can provide. We expect this to fit into an existing proceeding and be addressed in 2027.
To implement the grid utilization bill, creation of the metric should be relatively straightforward, but creating programs to improve the metric will require lengthy negotiations.
There are some tailwinds for this, and the metric will provide a further boost. There has been increased awareness in the past two years that utility profits are tied to grid spending. The more they spend, the higher their profits, and consumers pay the price in high rates.
Utilities have traditionally been quick to expand the electric grid whenever they can make the case that load is approaching the capacity of existing infrastructure, even if it’s a small handful of hours in the year when the capacity is really being used. Building highways large enough so there is never a rush hour slowdown would be extremely expensive. That is essentially what we have been doing with the electric grid.
The new metric will show how much load flexibility will be needed behind each substation to avoid costly grid expansion. On circuits with a low load factor, utilities can produce a day ahead dispatch command whenever usage is projected to come within a defined percentage of total capacity. Both front of the meter batteries and fleets of customer batteries should be able to sign up to respond to that signal.
What’s not to like about that? The technology is ready to scale, the mechanics should be feasible, and it can reduce rates for consumers. The biggest challenge is that creating effective programs to reduce grid spending gets at the heart of utility profits. We can expect a lot of creative maneuvering and claims of reliability risk.
There is hope that regulators will show some backbone. Frustration with California’s utilities has never been higher. On top of charging customers an arm and a leg, utilities are painfully slow to provide service. And their move this year to create a front group to push for relief from wildfire liability did not go over well. Their hand is not looking as strong as it once did.
It will still be some time before viable programs are up and running. In the meantime, we are installing 7,000 batteries every month, including an increasing number for commercial and industrial customers. We stand ready to compete as firm capacity as opportunities expand.
The post Golden State goes all in on VPPs appeared first on pv magazine Global.