Statkraft is progressing construction of its 57.7MWp Kilcush solar farm in County Offaly, marking the final stage in the development of Ireland’s first co-located wind, solar and battery storage project.
The company said construction began in May 2026, with energisation targeted for April 2027 and commercial operations expected by the end of that year.
Statkraft added that the solar farm will complement its wider Cushaling development, bringing together 55MW of wind generation, 57.7MWp of solar and a 22.8MW four-hour battery energy storage system (BESS).
However, the company warned that existing regulatory and system operator arrangements prevent the development from operating as a fully integrated hybrid project.
Full hybridisation would allow the wind and solar farms to charge the battery when the grid lacks sufficient capacity to accommodate all the electricity generated.
The battery could then discharge electricity onto the grid during periods of lower wind and solar generation, reducing reliance on imported gas.
Statkraft is calling for EirGrid and the Commission for Regulation of Utilities (CRU) to accelerate changes enabling grid capacity sharing, direct wires and hybridisation over the next 12 months.
Analysis by Cornwall Insight found that an unrestricted hybrid scenario could enable the use of an additional 1200GWh of renewable electricity annually and reduce renewable dispatch down by 16%.
The analysis also identified potential annual savings of €146m across the Single Electricity Market (SEM), alongside avoided gas generation of 2522GWh and emissions savings of 461 kilotonnes of CO2.
The potential carbon savings represent up to 10% of the annual emissions reductions required to achieve the SEM’s 2030 emissions target.
The Cushaling development follows Statkraft’s recent opening of Ireland’s first four-hour battery storage project.
“Now, over 15% of renewable power generated in Ireland is wasted,” said Statkraft senior vice president and country manager for Ireland and the UK Kevin O’Donovan.
“If we are serious about our energy future, both Eirgrid and the CRU must turn ambition into action and enable wind, solar and batteries to work as one.
“Specifically, the legislative changes recently put in place by Government to allow sharing of grid capacity, direct wires, as well as approving hybridisation need to be completed over the next 12 months.”